Stage one: the code edition and a fee that is not ours
New homes keep going up in Tulare. The City’s financial report shows new water connections every fiscal year from FY2014 through FY2023, never fewer than 179 and as many as 701, and FY2023 alone added 362 water connections and 333 sewer connections. Projects run from a single infill lot to subdivisions like Mission Creek, which the City’s 2024 environmental document describes as 255 single-family homes and a park at the southwest corner of Bardsley Avenue and Oakmore Street. Whatever the scale, two plumbing decisions get made before a shovel moves.
The first is which code the work answers to. Tulare’s Municipal Code still reads as adopting the 2022 California Plumbing Code, but the state sets the edition that counts: the 2025 California Building Standards Code took effect statewide on January 1, 2026, and Health and Safety Code 18938.5 places every permit application submitted on or after that date under it. On anything permitted this year, we lay out the plumbing to the 2025 edition, and if your drawings were finished last year we check the plumbing sheets against it before you submit.
The second is a charge you should budget for but never see on a plumbing estimate. Chapter 7.10 of the Municipal Code requires anyone seeking a building permit in the city to pay a groundwater overdraft mitigation fee before the permit issues. The City sets and collects it, and the money goes to recharge and surface water projects. It belongs in the permit column of your budget.
Stage two: the drains that disappear under concrete
On a slab build, the drain, waste and vent system below the floor goes in after the footings are dug and before any concrete. This is the least forgiving stage of the job. Each toilet flange, tub drain, shower drain and sink stub is set to plan dimensions, horizontal runs get their fall, and every pipe that crosses a footing gets a sleeve so the concrete never locks onto it. The system is then filled with water and held while the inspector looks.
Do not let anyone pour until that inspection is signed off. A stub in the wrong place costs a fitting while the trench is open. After the pour it means cutting finished concrete, patching and re-inspecting, and the schedule slips for every trade behind you.
Stage three: a service sized beyond the meter
Tulare meters every connection, homes included, and the City has swapped its residential hand-read meters for radio-read ones. Under Resolution No. 16-14, in effect since July 21, 2016, one inch is the minimum metered service for single-family homes as well as multi-family, commercial and industrial lots.
That one inch is the City’s minimum, not your design. The pipe between the meter and the house is sized from the plumbing code’s fixture-unit tables, the developed length of the run and the pressure available at the street. A deep lot, a two-story plan with three baths, or a second dwelling at the back can all need more pipe than the meter size suggests. We size the service line from the meter to the house from your actual fixture count, and the monthly bills from a radio-read meter make a quiet test of the new work: an empty house whose meter keeps advancing has a leak somewhere.
Stage four: laterals, parkways and the trees that come later
Many new lots get a street tree in the parkway, and Chapter 8.32 of the Municipal Code reaches straight into the plumbing. Root barriers are required on residential lots, new or existing, whenever street trees are planted in their parkways. No one may dig a trench within four feet of a street tree without the Director’s written permission. And damage a parkway tree does to sewer laterals, water service lines or meters is the responsibility of the property owner who is charged with caring for that tree.
For a new build, that means choosing the lateral and service routes before the landscape plan fixes the tree, keeping pipe and roots apart where the lot allows, and confirming the barrier actually goes in. A lateral laid under a sapling today is the owner’s root problem in the line a decade or two from now, with the code saying so in writing.
Stage five: top-out, trim and the record of what is in the walls
After framing, supply and vent piping runs through studs and plates, with nail plates wherever pipe sits close to a stud face, vents through the roof and shower valves set to the finished wall. The supply side is held under test for the rough inspection before insulation hides it. If the plan includes a gas range, a furnace or a gas water heater, the gas piping for those appliances gets sized and tested at this stage too.
Trim comes last: fixtures, angle stops, the water heater set and strapped, and the final inspection. Before drywall goes up, we photograph every wall that has pipe in it and give you the full set. Whoever mounts a television, hangs cabinets or adds a shelf in ten years will know exactly where not to drill, which is a record most finished houses never come with.